Substations

PS1 66/11 kV AIS


Owner : New Urban Communities Authority (NUCA)

Completion Date : 06/2026


Description

The project objective is to feed the expected demand load for thepumping Stations to Transport Nile River Water to capital Administrative Cityat Cairo Governorate

Scope of works

·    Project study and design

·    Feasibility study

·    Bid Documents Preparation

·    Bids Evaluation

·    Prepare Technical Evaluationreport with recommendation

·    Prepare Final evaluation reportwith recommendation

·    Prepare contract documents

·    Project Management

·    Detailed design review of thesubstation

·     Site Supervision of construction, testing & commissioning tillhanding over


Pictures